| 1. Site Information |
| Site |
Sierra Army Depot |
| Contact Person |
dmoore@siad.army.mil |
| Title |
Energy Manager |
| Address |
Sierra Army Depot |
| City |
Herlong |
| State |
California |
| Zip |
96113 |
| Country |
USA |
| 2. Business Type |
| Product Description |
Repair, maintenance & storage |
| SIC |
NA |
| 3. Air Compressor |
| Featured Air Compressor |
| Manufacturer |
NA |
| Package Model |
NA |
| Engine Model |
NA |
| Engine Rated Power (hp);bhp |
125 |
| Air Capacity @ Full Load (scfm) |
600 |
| Air Pressure @ Full Load (psig) |
100 |
| Summary of all air compressors at site |
NA |
| 4. Performance |
| Energy Consumption |
10.4 therms/hr |
| Emissions Levels (g/hp-hr) |
| Nox |
NA |
| CO |
NA |
| HC |
NA |
| PM |
NA |
| VOC/HAPS |
NA |
| 5. Duty Cycle |
| Shifts per Day |
1 to 2 |
| Days per Week |
4 |
| Weeks per Year |
50 |
| Hours per Year |
3650 |
| 6. Costs |
| Capital |
NA |
| Installation |
NA |
| 7. Purchasing Decisions |
| Who were the decision makers? |
HQAMC |
| Why were gas air compressors chosen? |
Savings compared to the cost of electricity |
| Did gas system replace electric unit? |
Yes |
| Would another gas unit be purchased? |
Yes |
| What are estimated savings? |
$16,000/yr (estimated) |
| What economic guidelines were used? |
NA |
| 8. Customer Satisfaction |
| Overall Customer Satisfaction (1 to 10 with 10 being highest) |
NA |
| 9. Notes |
| Heat recovery will be installed for space heating. |
| Source of Case Study |
USACERL |